When a work order is in a status that allows for cost recording, you can record various types of costs associated with its execution, such as labor, consumption, and miscellaneous costs.


Record labor

To record labor costs, follow these steps:

  1. Go to Work | Work Orders;
  2. Select the desired work order;
  3. Click Operations, then Labor;
  4. Click Create;

When filling in the labor record, the following points should be considered:

  • By default, the asset (equipment, tool, or location) is the one associated with the work order;
  • If the work order is for a route:
    1. Select the asset category;
    2. Select the corresponding asset;
  • Labor can be reported:
    • To the maintenance plan;
    • To the maintenance plan task;
    • To additional tasks;
  • The record date cannot be earlier than the work order creation date;
  • The record can only be linked to the authenticated user;
  • Labor can only be recorded if the work order status allows for cost recording;
  • The manager of the workshop to which the work order belongs can create, edit, and cancel records.

Record material consumption

There are several ways to record material consumption:

Record consumption

To record consumption, follow these steps:

  1. Go to Work | Work Orders;
  2. Select the desired work order;
  3. Click Operations, then Consumptions;
  4. Click Create and then Consumption;
  5. Fill in the necessary data;
  6. Click Save and New.

When filling in the record, the following points should be considered:

  • The record date cannot be earlier than the work order creation date;
  • By default, the asset is the one in the work order;
  • If the work order is for a route:
    1. Select the asset category;
    2. Select the corresponding asset;
  • Consumption can be reported:
    • To the maintenance plan;
    • To the maintenance plan task;
    • To additional tasks;
  • You can only select warehouses belonging to the company to which consumption will be reported;
  • Labor can only be associated with the authenticated user;
  • The manager of the workshop to which the work order belongs can create, edit, and cancel records;
  • If an externally managed warehouse is associated, you cannot select warehouses that are not externally managed in other consumption lines.

Record consumption via a requisition

To record consumption via a requisition, follow these steps:

  1. Go to Work | Work Orders;
  2. Select the desired work order;
  3. Click Operations, then Consumptions;
  4. Click Create, then Copy from Requisitions;
  5. Select the desired parts;
  6. Click Create Consumption;
  7. Validate the data;
  8. Click Save.

When filling in the record, the following points should be considered:

  • You can only record consumption if the work order status allows for cost recording;
  • You can only select company warehouses that are specified in the requisition;
  • The quantity recorded may not exceed that specified in the requisition;
  • The manager of the workshop to which the work order belongs can create, edit, and cancel records;
  • With a Technician role, you can only view warehouses with no restrictions or those with permitted access;
  • By default, the asset is the one specified in the work order;
  • If the work order is for a route:
    1. Select the asset category;
    2. Select the corresponding asset;

Record consumption at average cost

To record material consumption at average cost, follow these steps:

  1. In Settings | Work | Work Order Types, click the Create button to add a work order type;
  2. Go to the Costs tab and select the Use Average Cost Pricing option;
  3. Record consumption in the work order.

The formula used to calculate the average cost price (ACP) is as follows: ACP = [(Current Stock × Current ACP) + (Stock Entry × Entry Price)] / (Current Stock + Stock Entry).

Example:

Part P_001 is out of stock. Two entries were made for this part:

  • Entry of 10 units at €1.00: ACP = 10 x 1,00 € / 10 = 1,00 €;
  • Subsequent entry of 20 units at €0.50: ACP = [(20 x 0,5 €)  +  (10 x 1 €) ] / 30 = 0,67€;

Record miscellaneous costs

To record miscellaneous costs, follow these steps:

  1. Go to Work | Work Orders;
  2. Select the desired work order;
  3. Click Operations, then Misc Costs;
  4. Click Create;
  5. Fill in the necessary fields;
  6. Click:
    • Save and New, to save and access a new registration form;
    • Save, to save the entered data;
When filling in the miscellaneous costs record, the following points should be considered:
  • By default, the asset is filled in with the asset from the work order;
  • If the work order is for a route:
    1. Select the asset category;
    2. Select the corresponding asset;
  • Miscellaneous costs can be reported:
    • To the work order;
    • To the maintenance plan;
    • To additional tasks;
  • The record date cannot be earlier than the work order date;
  • It is mandatory to enter an asset for routes;
  • Costs can only be reported if the work order allows for cost recording;
  • The reported amount must fall within the limits (minimum and maximum amounts) defined for the cost type;
  • The manager of the workshop to which the work order belongs can create, edit, and cancel records;