--- title: "How to record costs on a work order?" slug: "1723138684" tags: ["Work"] updated: 2026-07-22T15:02:44Z published: 2026-07-22T15:03:12Z canonical: "help.ila.cegid.com/1723138684" --- > ## Documentation Index > Fetch the complete documentation index at: https://help.ila.cegid.com/llms.txt > Use this file to discover all available pages before exploring further. # How to record costs on a work order? - [x] PT - [x] ES --- When a work order is in a status that allows for **cost recording**, you can record various **types of costs** associated with its execution, such as labor, consumption, and miscellaneous costs. --- ## Record labor To record labor costs, follow these steps: 1. Go to **Work | Work Orders**; 2. Select the desired **work order**; 3. Click **Operations**, then **Labor**; 4. Click **Create**; When filling in the labor record, the following points should be considered: - By default, the **asset** (equipment, tool, or location) is the one associated with the **work order**; - If the work order is for a **route**: 1. Select the **asset category**; 2. Select the corresponding **asset**; - Labor can be reported: - To the maintenance plan; - To the maintenance plan task; - To additional tasks; - The record date cannot be **earlier** than the work order creation date; - The record can only be linked to the authenticated user; - Labor can only be recorded if the work order status allows for **cost recording**; - The manager of the workshop to which the work order belongs can **create**, **edit**, and **cancel** records. --- ## Record material consumption There are several ways to record **material consumption**: **Record consumption** To record consumption, follow these steps: 1. Go to **Work | Work Orders**; 2. Select the desired **work order**; 3. Click **Operations**, then **Consumptions**; 4. Click **Create** and then **Consumption**; 5. Fill in the necessary data; 6. Click **Save and New**. When filling in the record, the following points should be considered: - The record date cannot be **earlier** than the work order creation date; - By default, the **asset** is the one in the **work order**; - If the work order is for a route: 1. Select the asset **category**; 2. Select the corresponding **asset**; - Consumption can be reported: - To the maintenance plan; - To the maintenance plan task; - To additional tasks; - You can only select **warehouses belonging to the company** to which consumption will be reported; - Labor can only be associated with the authenticated user; - The manager of the workshop to which the work order belongs can **create**, **edit**, and **cancel** records; - If an **externally managed warehouse** is associated, you cannot select warehouses that are not externally managed in other consumption lines. **Record consumption via a requisition** To record **consumption** via a **requisition**, follow these steps: 1. Go to **Work | Work Orders**; 2. Select the desired **work order**; 3. Click **Operations**, then **Consumptions**; 4. Click **Create**, then **Copy from Requisitions**; 5. Select the desired parts; 6. Click **Create Consumption**; 7. Validate the data; 8. Click **Save**. When filling in the record, the following points should be considered: - You can only record consumption if the work order status allows for **cost recording**; - You can only select **company warehouses** that are specified in the **requisition**; - The **quantity recorded** may not exceed that specified in the **requisition**; - The manager of the workshop to which the work order belongs can **create**, **edit**, and **cancel** records; - With a **Technician** role, you can only view warehouses with no restrictions or those with permitted access; - By default, the **asset** is the one specified in the **work order**; - If the work order is for a route: 1. Select the asset **category**; 2. Select the corresponding **asset**; **Record consumption at average cost** To record material consumption at average cost, follow these steps: 1. In **Settings | Work | Work Order Types**, click the **Create** button to add a work order type; 2. Go to the **Costs** tab and select the **Use Average Cost Pricing** option; 3. Record consumption in the work order. The formula used to calculate the average cost price (ACP) is as follows: **ACP = [(Current Stock × Current ACP) + (Stock Entry × Entry Price)] / (Current Stock + Stock Entry).** **Example:** Part **P_001** is out of stock. Two entries were made for this part: - Entry of 10 units at €1.00: **ACP = 10 x 1,00 € / 10 = 1,00 €**; - Subsequent entry of 20 units at €0.50: **ACP = [(20 x 0,5 €) + (10 x 1 €) ] / 30 = 0,67€;** --- ## Record miscellaneous costs To record miscellaneous costs, follow these steps: 1. Go to **Work | Work Orders**; 2. Select the desired **work order**; 3. Click **Operations**, then **Misc Costs**; 4. Click **Create**; 5. Fill in the necessary fields; 6. Click: - **Save and New**, to save and access a new registration form; - **Save**, to save the entered data; When filling in the miscellaneous costs record, the following points should be considered: - By default, the asset is filled in with the asset from the work order; - If the work order is for a route: 1. Select the asset **category**; 2. Select the corresponding **asset**; - Miscellaneous costs can be reported: - To the work order; - To the maintenance plan; - To additional tasks; - The record date cannot be **earlier** than the work order date; - It is mandatory to enter an **asset** for **routes**; - Costs can only be reported if the work order allows for **cost recording**; - The reported amount must fall within the limits (minimum and maximum amounts) defined for the cost type; - The manager of the workshop to which the work order belongs can **create**, **edit**, and **cancel** records;